Road construction and maintenance projects

ALLEN COUNTY

Interstate 75 pavement repair: Interstate 75 under Stewart Road (MM 129-128) will have lane closures for pavement repairs according to the schedule below:

Northbound passing lane on Monday, Sept. 9

Southbound both lanes and northbound driving lane are complete.

State Route 12, State Route 115, State Route 613 resurfacing: State Route 12, State Route 115, and State Route 613 in Putnam, Allen, and Hancock counties at the following locations will be restricted to one lane through the work zone beginning Aug. 19 for resurfacing.

State Route 12: Throughout Allen County.

State Route 115 slide repair: State Route 115 between Cole Street and Kissing Hollow Drive closed on May 13 for approximately 90 days to repair the slope and replace a culvert. The contracted work is behind schedule; the latest estimate to reopen is the week of Sept. 9. Work is expected to take place on the weekends to expedite the completion. Visit the project webpage for more information: Detour: SR 65 to U.S. 30, back to SR 115.

State Route 117/State Route 309 traffic signal: Traffic signal work may impact traffic at the intersection of Bellefontaine Avenue, Kibby Street, Leonard, and Harding Highway in the city of Lima. Lanes may close, and flaggers may be necessary.

AUGLAIZE COUNTY

Interstate 75 Lane Shift – Expect two lanes on I-75 in each direction. Southbound traffic in the left lane will cross over into a contraflow lane on the northbound side just south of the rest areas starting Thursday, June 6 through October 2024. Vehicles in the contraflow lane will not have access to exit 113 for SR 67. Drivers will re-enter the southbound driving lane just north of Middle Pike. Crews will be reconstructing the southbound travel lane bridge. This new traffic pattern will maintain two lanes of traffic in each direction. This shift is weather dependent.

Interstate 75 Lane Closures – Expect intermittent overnight lane closures on I-75 in both directions between Middle Pike and Hengstler Road from 6 p.m. to 7 a.m. starting Monday, March 18 through Friday, November 1. Crews will be performing bridge work.

HARDIN COUNTY

State Route 31 reconstruction: Main Street between Ohio Street and Carrol Street in the city of Kenton closed on March 4 for 240 days for reconstruction, curb and gutter, and sewer. Detour: U.S. 68/Detroit St. to Letson Ave., back to SR 31/Main St.

State Route 81 culvert replacement: State Route 81 at the intersection of County Road 95, approximately four miles east of the village of Ada, will close Sept. 9 for approximately 10 days for a culvert replacement. Detour: U.S. 68 to U.S. 30 to SR 235, back to SR 81.

PUTNAM COUNTY

State Route 12, State Route 115, State Route 613 resurfacing: State Route 12, State Route 115, and State Route 613 in Putnam, Allen, and Hancock counties at the following locations will be restricted to one lane through the work zone beginning Aug. 19 for resurfacing.

State Route 12

Putnam County

From the village of Vaughnsville to the Allen County line.

From the Allen County line to the west corporation of Columbus Grove.

From the east corporation of Columbus Grove to the Hancock County line.

State Route 115

Putnam County

Through the village of Kalida (no work will take place during Pioneer Days, Sept. 5-8)

State Route 613

Putnam County

Through the village of Leipsic.

State Route 65 Pavement Repairs: State Route 65 between the village of Leipsic and the Henry County line, will be reduced to one lane through the work zone the week of Sept. 2 for pavement repair.

State Route 108 pavement repair: State Route 108 between State Route 15 and the Henry County line will be restricted to one lane through the work zone for pavement repairs.

State Route 694 pavement repair: State Route 694 between State Route 114 and the village of Glandorf will be restricted to one lane through the work zone for pavement repairs.

State Route 696 pavement repair: State Route 696 between the Allen County line and the village of Pandora will be restricted to one lane through the work zone for pavement repairs.

VAN WERT

U.S. 30 rest area reconstruction: The U.S. 30 rest areas between State Route 49 and U.S. 127 in Van Wert County closed on January 11 for approximately one year for complete reconstruction of the buildings.

U.S. 30 bridge repair: Converse Roselm Road and Stripe Road over U.S. 30 are closed until further notice as a safety precaution due to a bridge strike caused by an over-height vehicle. Repair is expected to take place in 2024.

U.S. 127 resurfacing: U.S. 127 between the Mercer County line the city of Van Wert is restricted to one lane for resurfacing.

State Route 81 reconstruction: State Route 81 between Willshire Eastern Road and Harrison Willshire Road, just east of the village of Willshire closed on May 6 for approximately 150 days to raise the roadway profile and replace two culverts. Access for local traffic to all properties will be maintained throughout construction. Detour: SR 49 to U.S. 33 to SR 118, back to SR 81.

Leeson Avenue reconstruction: Leeson Avenue between Shannon Street (State Route 118) and Rose Drive in the city of Van Wert closed on Feb. 7 for 245 days for reconstruction including curb and gutter, storm sewer, and a multi-use path on the north side of the roadway.

ONLY ON LIMAOHIO.COM